Im porting mpx, mpp to P5
In the Open Standard
Hady Shendy, PMPMember for 20 years 4 months
- Created
- 2
- 4
0
I use WBS Chart Pro from www.criticaltools.com to create the WBS on simply way
Then I do 2 ways of out put:
1- Save as MPX file, or
2-automatically open MS Project then save it MPP files
Try to import any of these files to P5; I have the same problem as below:
* Each WBS level represent as WBS level, it’s OK!
*but also represent it as an activity also
And as we knew the activities are the last level on WBS
As a prof. project manager you need to create WBS 1st then you go to network diagram, therefore believe me the upper program is the right tool for that
Please advice
Then I do 2 ways of out put:
1- Save as MPX file, or
2-automatically open MS Project then save it MPP files
Try to import any of these files to P5; I have the same problem as below:
* Each WBS level represent as WBS level, it’s OK!
*but also represent it as an activity also
And as we knew the activities are the last level on WBS
As a prof. project manager you need to create WBS 1st then you go to network diagram, therefore believe me the upper program is the right tool for that
Please advice
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?