Values on top of histogram??

Suraj BhattMember for 22 years 4 months
Created
7
3
0
How can I show values on the top of the resource histogram (in P5)as was possible in P3??
Thanks in advance!
Suraj

7 replies

Oldest first
  1. 0
    Karim Mounir ·
    u can’t, u have to dbl. click on every bar in the graphical report to show its value.

    Or u can go for a tabular report and export it to excel and make a manual histogram which show values on the top of the bars !!!
  2. 0
    Marcio Sampaio ·
    one more "walk back" on P3e / P5 versions ... sometimes i miss P3 ...
  3. 0
    Suraj Bhatt ·
    Well..It has its drawback but has good merits too..
    Like yesterday I was asked to make a small programm in 30 min for presentation.It was possible to complete it in allocated time because of the ease of adding ,shifting,copy-pasting WBS In P5.It was not possible on P3.
    Cheers
    Suraj
  4. 0
    Marcio Sampaio ·
    Yes ... i said "sometimes"

    Regards.
  5. 0
    Rashid Iqbal ·
    Suraj,

    You wrote that the values could be shown/printed over the histograms in P3. Could you please let me know as to how it can be done.

    Thanks.

    Regards
    Rashid
  6. 0
    Armando Moriles ·
    Hi, I think at Resource/Cost Graphics Report, just check Display Data Values.
  7. 0
    Rashid Iqbal ·
    Thanks for responce. Actually i mistakingly got an idea that these data value can be shown in ’Res/Cost Profile’ which one can print under the gantt chart.

    Regards
    Rashid

Log in or join to reply