Peak Manpower in the Resource Histogram
In the Open Standard
Glenn Dexter UbaldoMember for 17 years 4 months
- Created
- 12
- 7
0
Hello everyone,
I would like to ask if anyone could explain to me how to show the Peak manpower either on report or by histogram in
P6 because I use this option often in P3 but know our current project requires us to use P6 but I cannot locate this option. I would very much appreciate if any one could help me.
Glenn,
I would like to ask if anyone could explain to me how to show the Peak manpower either on report or by histogram in
P6 because I use this option often in P3 but know our current project requires us to use P6 but I cannot locate this option. I would very much appreciate if any one could help me.
Glenn,
12 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?