Peak Manpower in the Resource Histogram

Glenn Dexter UbaldoMember for 17 years 4 months
Created
12
7
0
Hello everyone,

I would like to ask if anyone could explain to me how to show the Peak manpower either on report or by histogram in
P6 because I use this option often in P3 but know our current project requires us to use P6 but I cannot locate this option. I would very much appreciate if any one could help me.

Glenn,

12 replies

Oldest first
  1. 0
    David Kelly ·
    P3 offered "Total, Peak, Average"

    P6 just has "total or average"
  2. 0
    Eric EVRARD ·
    Hello,
    Go to the "resource usage profile", right click on the histogram and select "Resource Usage Profile Options".
    In Additional Data Options, select "Show Limits" and "Show Overallocation", it should works
    Regards
    Eric
  3. 0
    Glenn Dexter Ubaldo ·
    Dear Eric,

    I tried this option and it is shows the over allocated budgedted units in histogram form but is it possible in P6 to generate a report in tabular form showing the average, peak & total budgeted quantity like in P3. i need this values because I am presenting the manpower histogram in excel. your response would be very much appreciated.

    Thanks,
    Glenn
  4. 0
    Eric EVRARD ·
    Hello Glenn,
    I don’t know If P6 do this, I guess that you can generate a report with those parameter in the "Reports" features but I am not familiar with it.
    Give me your mail adress I will forward you a document relating how I manage to export data in excel to generate Curves and Histograms
    Regards
  5. 0
    Glenn Dexter Ubaldo ·
    Hello Eric,
    Here is my email adress glenn_dexter@yahoo.com
    Thanks for your time.

    Glenn
  6. 0
    R. Catalan ·
    Eric,

    Pls send me a copy to planning_me@yahoo.com

    Thanks,
    R. Catalan
  7. 0
    Kalpesh Dalvi ·
    Can you please send a copy at Kalpesh.Dalvi@kcm.co.zm.

    Thanks in advance
  8. 0
    Artur Correa ·
    Hello Eric,

    Can you please also send a copy at correa1980@gmail.com

    Thank you in advance
    Artur
  9. 0
    Jojie Pepito ·
    Can you [lease send a copy at jpepito78@yahoo.com

    thanks!

    jojie
  10. 0
    Mohammed Amjad Ghaniwala ·
    Hello Eric,

    Please send me a copy also at amjad.ghaniwala@gmail.com.

    Thanks,
    Amjad
  11. 0
    Neal Walsh ·
    Hi Eric,

    Could you please also send me a copy?

    waltav@hotmail.com

    thanks very much.....

    Walshy
  12. 0
    A.Jaffer Sadiq ·

    Can you please send a copy at

    Can you please send a copy at jafferplanner@gmail.com

    Thanks in advance

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?