How to show Progress on Baseline Bar

Hengxiang ShenMember for 22 years 9 months
Created
1
3
0
I just move from P3 3.1 to P3 E/C 5.0. In 3.1 it is very easy to set the physical progress on baseline bar, but in 5.0 I set the progress bar same row position as baseline but the start point is not same as baseline start point and just start same as current bar start point, so the physical progress just in the middle of baseline bar. How can i do?

1 reply

Oldest first
  1. 0
    David Kelly ·
    shen,

    Primavera has no facility to do this.

    However you can use a global change create a pair of user defined dates which represent the liquidated part of the baseline bar, and use those dates to draw a bar which shows progress against the baseline.