Resource allocation by week - can it be done??
In the Open Standard
Chris FrankMember for 20 years 1 month
- Created
- 3
- 2
0
I’m looking to adjust my resource level on a weekly basis as I will have more men available later in the project is there a way to do thison a single line activity of 8 weeks??
At the moment it allocates the budgeted hours equallly over the duration of the activity.
At the moment it allocates the budgeted hours equallly over the duration of the activity.
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?