How to break an activity in P3 ec V.5

Sean MoghimiMember for 19 years 11 months
Created
3
2
0
Hi dear planners

Can anyone help regarding followings:

1) The way to break an activity into 2 or more parts in such a way that it appears in the bar chart. Therefore, part of activity will happen in such a date and the other part will happen other time. (Traditionally I could do it with P3 V. 3.1)

2) Is there any ebook or manual for P3 e/c V.5 available for free in the web?

Kind regards,
Shahab.

3 replies

Oldest first
  1. 0
    Alex Wong ·
    Shahab

    you mean subspend and resume??

    if it is , then the quick answer is yes you can do that in P5

    Cheers

    Alex
  2. 0
    Sean Moghimi ·
    Dear Alex

    Thanks for the message. If you mean suSpend and resume, yes i mean the same, that sounds good. would you give me more advices on how to do it in V.5 plz.?

    Regards.
  3. 0
    Alex Wong ·
    Shahab

    Please find the following for Primaera Help menu

    "At some point in the project, you may need to stop work on an activity for a period of time. Indicate this interruption by specifying suspend and resume dates in the Status tab of Activity Details.



    Display Activity Details.

    Click the Status tab.

    In the Activities window, select the activity you want to suspend.

    In the Status tab, enter a Suspend date.

    When the activity resumes, enter a Resume date.

    "

    Good luck

    Alex