Primavera Notebook for activities as a record of delays
In the Open Standard
Jan HlavacekMember for 19 years 11 months
- Created
- 7
- 6
0
Dear forum members, I am using on our project the Notebook in order to record reasons for delays for particular activities. It works fine, only problem is that I cannot export the notebooks nor I cannot create nice reports - for instance only for activities which have a non-blank notebook - I cannot filter them out.
My idea which doesn’t seem to be very practical would be to introduce an extra custom activity code which would have to be filled for activities which do have a notebook. This activity code would than be used for filtering.
Any suggestions perhaps, should I use the Issues instead? Thank you, Jan.
My idea which doesn’t seem to be very practical would be to introduce an extra custom activity code which would have to be filled for activities which do have a notebook. This activity code would than be used for filtering.
Any suggestions perhaps, should I use the Issues instead? Thank you, Jan.
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?