Hi!
I have made a program without loading resources in P3ec ver. 5.
When I import it in P3 only 1 level of WBS is imported.I have tried several times.There are 4 levels of WBS in the actual program.
Kindly suggest where I am going wrong??

Thanks
Suraj

1 reply

Oldest first
  1. 0
    Ronald Winter ·
    The P5 Help file has this to say about exporting WBS’s to P3,

    The Project Management module supports a maximum of 25 levels with an unlimited number of characters. P3 3.x supports 20 WBS levels with a limit of 48 characters. The Project Management module will export as many levels as possible until the limit of 48 characters or 20 levels is reached.

    I hope that this helps. Good luck!