Shading for Holidays

Matthew LovkisMember for 19 years 10 months
Created
2
1
0
Hi Guys,

I’m using P3e at the moment and I was wondering if anyone knows how to create a shaded area over designated non-work intervals like the christmas holidays.

I’d love to know how.

Cheers.

Matthew Lovkis

2 replies

Oldest first
  1. 0
    Karim Mounir ·
    Hi Matthew,

    U can make a "Curtain" to highlight the required timeline.
    Click on "View"-->"Attachments"-->"Curtain"-->"Add Curtain"

    Select your Start/End dates and also the fill pattern & its color.

    Merry Xmas.

    Regards.
  2. 0
    Matthew Lovkis ·
    Thanks tonnes!!

    That was exactly what I was looking for.

    Cheers and Merry Xmas to you too,

    Matthew Lovkis