PPlanet,

How are people managing the anuual leave of their resources?

If you have hundreds of resources what is the most efficient way?

Are you using resource calendars? Who manages the calendars?

6 replies

Oldest first
  1. 0
    Paul Harris ·
    One at a time with a lot of effort. Some companies set up a link to their HR module but this takes a bit of effort and funds.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
    www.eh.com.au
  2. 0
    Alex Wong ·
    Hi

    We only manage holiday/leave more than 3 days and 2 weeks in advance. Because, if it is within the next 2 weeks, it will be not worth it to change the entire plan.

    With Paul recommendation, we cannot apply to it simply because our HR department is very lazy, they only record leave in the Past not the future. Because they said it will be too much maintenance work if the leave application is withdrawn/modify etc...

    HTH

    Alex
  3. 0
    Oliver Melling ·
    I think a good idea for Primavera is to include the power to edit resource calenders via the timsheets module.
  4. 0
    Charleston-Joseph Orbe ·
    Previously,

    I worked in a construction company with more than 20,000 ++ employee.

    They did not use Primavera P3, P5 or other planning software to manage annual leave.

    they were able to manage seamlessly.

    The secrets:

    Hire low paid clerks from third world countries.

    common sense

  5. 0
    Oliver Melling ·
    There is no such thing as low paid in the UK, we have a national minimum wage.
  6. 0
    Lina Claud ·

    Hi, old post, but I want

    Hi, old post, but I want share with you a free solution I found to manage leave and time-off for some emplyees or a lot of employees, the solution is a software web-based, it's called offdays.eu , I manage leave employees with it and I enjoy it!