In my schedule I have one problem as following:

Activity A and B has relationship FS(no lag), Finish date of A is 16-May-07, normally the start date of B is 17-May-07, but in my schedule the start date of B is 16-May-07 same as the finish date of A. In my schedule I have 3 type of calendar but this problem happened if activities have same calendar or not.
Please give me the suggestion.

Thanks,
Shen Hengxiang

2 replies

Oldest first
  1. 0
    Mk Tse ·
    check the planning unit. If all in day, then check the working hour per day.

    By default installation, it is 8hr per day. When do progress input by drag on bar instead of type in the value, the result may be fall into some decimal value and cause the problem
  2. 0
    Alex Wong ·
    My suggestion is pretty much the same, check the finish activity finish time. if it finish @ 00:59 is different from finish @ 17:59 where you successor will start next date.
    Go Edit/User Preferece/Dates/Time/12hr or 24 hrs

    HTH

    Alex