Resource Calendar

Matthew LovkisMember for 19 years 10 months
Created
2
2
0
Hi there, I am having trouble getting P3e to recognise an activity and a resource as using a particular calendar. I have created the calendar "On Site 6 Day 64 Hr" and as the name suggests it specifies work to take place over 6 days and 64hrs per week. About 10.6 hours a day. I have applied the calendar to both the activity and the resource BUT P3e still calculates the man hours so that ’units per time’ equals 100% for an 8 HOUR DAY. Why is this? And how can I change it? I am going crazy. I want ’units per time’ to equal 100% for the ~10 HOUR DAY. Any help would be appreciated. Thanks tonnes, Matthew Lovkis

2 replies

Oldest first
  1. 0
    Alex Wong ·
    Matthew

    Is your activity type is Fix Unit/Time, if that is the case then you cannot change the Unit/time for the activity.

    What I suggest is to change you activity type to fix duration (Be careful to check with your acitivity duration) change the resource UPT, change back the activity type to fix UPT.

    This should do the job

    HTH

    Alex
  2. 0
    Matthew Lovkis ·
    Thanks a lot Alex, I’ll give it a go.

    Cheers,

    Matthew Lovkis