Resource Calendar
In the Open Standard
Matthew LovkisMember for 19 years 10 months
- Created
- 2
- 2
0
Hi there,
I am having trouble getting P3e to recognise an activity and a resource as using a particular calendar.
I have created the calendar "On Site 6 Day 64 Hr" and as the name suggests it specifies work to take place over 6 days and 64hrs per week. About 10.6 hours a day.
I have applied the calendar to both the activity and the resource BUT P3e still calculates the man hours so that ’units per time’ equals 100% for an 8 HOUR DAY.
Why is this? And how can I change it? I am going crazy.
I want ’units per time’ to equal 100% for the ~10 HOUR DAY.
Any help would be appreciated.
Thanks tonnes,
Matthew Lovkis
2 replies
Oldest firstLog in or join to reply