Primavera P3E/C version 5

Kevin TonMember for 19 years 11 months
Created
3
2
0
Hello,

Has anyone ever experienced P3E/C very slow?

Recently, my project migrated from p3 to P3E/C with 8000 activities, whenever I made any change, it just took ages to finish?

Any suggestion would be very appreciated.

3 replies

Oldest first
  1. 0
    David Forrest ·
    Check your PC’s virtual memory and adjust to maximum
  2. 0
    Alex Wong ·
    Kevin

    Are you using a networked P3e??
    Sometime the network traffic is the bottle neck of the slow respond issue.
    Talk to your IT helpdesk (Standard reply will be we do not have any issue with our intranet ^&*)
    HTH

    Alex
  3. 0
    Kevin Button ·
    Just a thought, is the project rescheduling after you make a change? There is a scheduling option called ’Schedule automatically when a change affects dates’. This option is OK for small schedules but with 8000 activities I would have this switched off.

    KB