How to filter out only those activities driving a task?
In the Open Standard
David PodmoreMember for 20 years 5 months
- Created
- 4
- 3
0
I’ve just been asked if I can select a task towards the tail of a project (not neccessarily on THE critical path) and only display those tasks driving it. In effect a selective "critical path" in its own right if you see what I mean. Sounds like a good idea for a TOOLS button but there you go...
4 replies