Actuals on Level of Effort Activities

Matthew LovkisMember for 19 years 10 months
Created
1
2
0
Hi Guys,

I can’t seem to update actuals on Level-of-Effort activities. Whenever I schedule the project the actuals return to zero, no matter what value I have entered in the actuals column.

Would love to know why, and if this can be changed.

Thanks a lot,

Cheers,

Matthew Lovkis

1 reply

Oldest first
  1. 0
    David Forrest ·
    You need to update %age complete !!

Log in or join to reply