Duration Type / Percent Complete - Absolute Confusion
In the Open Standard
Matthew LovkisMember for 19 years 10 months
- Created
- 0
- 2
0
Hi There,
I am struggling to come to terms with the duration type and percent complete functions of P3e. I have read numerous texts and everything I can find on the subject.
All I want is to be able to update an activity where the At Complete Duration doesn’t change when I update the Actual Units.
However when I have an activity that is Fixed Duration and Units, and the percent complete type is Units... when I update the units and the data date... it increases the At Complete Duration. How can I possibly keep the at complete duration the same throughout?
Thanks,
Matt Lovkis
I am struggling to come to terms with the duration type and percent complete functions of P3e. I have read numerous texts and everything I can find on the subject.
All I want is to be able to update an activity where the At Complete Duration doesn’t change when I update the Actual Units.
However when I have an activity that is Fixed Duration and Units, and the percent complete type is Units... when I update the units and the data date... it increases the At Complete Duration. How can I possibly keep the at complete duration the same throughout?
Thanks,
Matt Lovkis
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?