Current progress against baseline?
In the Open Standard
Kevin UttingMember for 22 years 3 months
- Created
- 7
- 3
0
Does anyone know where the option to view current progress on the baseline bar is?
In P3 v3.1 I used to be able to show a progress drop line as a red saw tooth line joining current progress on my target bar.
I can’t show the red-line in P3e which I can live with, but can I show my baseline bar with current progress % on that bar?
When I click view > Bars... and select just my primary baseline bar and my % complete bar and my activity started late it shows my progress in the middle of the baseline bar commencing from it’s actual start date and not on the planned start date as I would like.
Does anyone have any suggestions?
In P3 v3.1 I used to be able to show a progress drop line as a red saw tooth line joining current progress on my target bar.
I can’t show the red-line in P3e which I can live with, but can I show my baseline bar with current progress % on that bar?
When I click view > Bars... and select just my primary baseline bar and my % complete bar and my activity started late it shows my progress in the middle of the baseline bar commencing from it’s actual start date and not on the planned start date as I would like.
Does anyone have any suggestions?
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?