P3 V5 Project Management- Resource Curves

Donovan GovenderMember for 20 years 10 months
Created
2
2
0
After creating your resource curves - Histograms how do one save it and where does it save to??

2 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Danovan,

    Your query is not clear. I’m not sure if you are after on the resource curves that drive your resources profile or tracking module of P3 v5.

    Resources curve are save global or default which enable you to select which curve are your going to use for each resources assigned on your activity task.

    If you are after on tracking module you can save it available to all user or current user only on the tracking layout.

    Hope this help.

    Regards,

    Rodel
  2. 0
    Kevin Button ·
    View, Layout, Save As then assign a layout name.

    KB