P3e - Application License Key

Marc winslettMember for 23 years 5 months
Created
1
2
0
Hi - I have just installet v5 as a standalone, but I selected the wrong license file which is now out of date. The software loaded ok with this license but now won’t run (just get a dialogue box saying "Application License key has expired etc . . . ) I have the correct one, but don’t know how to assign the valid license to the software. Can anybody help please?

1 reply

Oldest first
  1. 0
    Karim Mounir ·
    Marc,

    Click on Start --> Programs --> Primavera --> Help and Utilities.

    Now click on Database Configuration, next choose "Administration Tasks", next choose "Configure Database License", then choose your database and enter the administrative username/password.

    Now click on "Open" and browse to the location of the new License file.

    Regards,
    Karim