How to sync Activity Dates & Resource dates
In the Open Standard
Rama KrishnanMember for 19 years 11 months
- Created
- 2
- 2
0
Resource start & finish dates are not in line with activity start & finish dates.
I have a problem - when I extend activities resources assigned do not follow the activities.
I use a Non Labour resource. So by I have to default it to Non driving resource.
Is there a way to sync the resource dates & activity dates together. I prefer activity to drive the resource than the other way round for my application.
I also have a funny problem - When I drag the activity to change finish dates using mouse the resource assigned doe not follow. But instead I manually update the planned duration the resource follows & is in sync.
Anybody experiencing this problem?
All my activities are FixedDuration/Units setup. Resource assigned is one resource but non-labour. I have assigned a non -linear curve to the resource.
Rama
I have a problem - when I extend activities resources assigned do not follow the activities.
I use a Non Labour resource. So by I have to default it to Non driving resource.
Is there a way to sync the resource dates & activity dates together. I prefer activity to drive the resource than the other way round for my application.
I also have a funny problem - When I drag the activity to change finish dates using mouse the resource assigned doe not follow. But instead I manually update the planned duration the resource follows & is in sync.
Anybody experiencing this problem?
All my activities are FixedDuration/Units setup. Resource assigned is one resource but non-labour. I have assigned a non -linear curve to the resource.
Rama
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?