Skip to content

Resources on LOE Activities

Matthew LovkisMember for 19 years 10 months
Created
2
2
0
Hi All,

I’m going nuts with my schedule at the moment!

I am updating resource allocations at the moment and after I spent a long time updating the resources on my Level of Effort activities, I scheduled the project, AND all of the hours changed on the L.O.E. activities.

How can I prevent this from happening?

I want to be able to regularly update hours associated with a Level of Effort activity. And once I press F9 I don’t want the hours to change.

Thanks a lot,

Matt Lovkis

2 replies

Oldest first
  1. 0
    Karim Mounir ·
    Hi,
    U can check the post titled "Applying Progress To A Level Of Effort Activity" in p3 e/c forum.
  2. 0
    Matthew Lovkis ·
    Thanks tonnes mate,

    That was the one!

    It was the recalculate toggle that needed to be unchecked.

    Cheers,

    Matt Lovkis

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?