Resources on LOE Activities
In the Open Standard
Matthew LovkisMember for 19 years 10 months
- Created
- 2
- 2
0
Hi All,
I’m going nuts with my schedule at the moment!
I am updating resource allocations at the moment and after I spent a long time updating the resources on my Level of Effort activities, I scheduled the project, AND all of the hours changed on the L.O.E. activities.
How can I prevent this from happening?
I want to be able to regularly update hours associated with a Level of Effort activity. And once I press F9 I don’t want the hours to change.
Thanks a lot,
Matt Lovkis
I’m going nuts with my schedule at the moment!
I am updating resource allocations at the moment and after I spent a long time updating the resources on my Level of Effort activities, I scheduled the project, AND all of the hours changed on the L.O.E. activities.
How can I prevent this from happening?
I want to be able to regularly update hours associated with a Level of Effort activity. And once I press F9 I don’t want the hours to change.
Thanks a lot,
Matt Lovkis
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?