Activity Updates
In the Open Standard
Matthew LovkisMember for 19 years 10 months
- Created
- 1
- 1
0
Hi Folks,
Is there any way that I can drag the progress spotlight over a bunch of activities, then when I press schedule the activity status’ are updated according to the progress spotlight?
For example if I drag the PS over an activity that hasn’t started. When I press schedule, it will have automatically started the activity for me.
Is this possible?
Any help would be fantastic.
Cheers,
Matt Lovkis
Is there any way that I can drag the progress spotlight over a bunch of activities, then when I press schedule the activity status’ are updated according to the progress spotlight?
For example if I drag the PS over an activity that hasn’t started. When I press schedule, it will have automatically started the activity for me.
Is this possible?
Any help would be fantastic.
Cheers,
Matt Lovkis
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?