Activity Updates

Matthew LovkisMember for 19 years 10 months
Created
1
1
0
Hi Folks,

Is there any way that I can drag the progress spotlight over a bunch of activities, then when I press schedule the activity status’ are updated according to the progress spotlight?

For example if I drag the PS over an activity that hasn’t started. When I press schedule, it will have automatically started the activity for me.

Is this possible?

Any help would be fantastic.

Cheers,

Matt Lovkis

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Hi Matthew,

    You can use progress spotlight to update your activities. Highlight your activities using progress spotlight then select Tools-> Update Progress and tick all highlighted activities and click Apply.

    Note: You will notice that the date specified is based on your progress spotlight.

    Regards,
    Rodel