Resource Loading
In the Open Standard
Ife OlykeMember for 19 years 8 months
- Created
- 7
- 2
0
Folks,
I would be very grateful if anyone can help me with this.
I have a P6 schedule:
(a) My data date is 7th Nov 09 07:30AM
(b) Under Reports>Report Group:Resources, I created a report profile with timescale start set to DD and date interval set to week
When I run the report, the data spread starts from 2nd November 09 as opposed to 7th Nov 09... Who has an idea why this is happening???
Thanks...