Showing Non Work Period in Bar Chart in P3e

Nitin NaikMember for 21 years 8 months
Created
3
1
0
Folks,

Does anyone know how to show a non working period in bar chart in P3e Version 5.0

Currently it can be shown using ’curtain’ function but it needs to done manually for each non work period.

Look forward to your replies

Cheers

Nitin

3 replies

Oldest first
  1. 0
    Arthur Godbeer ·
    View/Bars/Bar Settings/Bar Necking Settings.
  2. 0
    Nitin Naik ·
    Hi,

    Thanks Arthur for your reply.

    I was mainly after showing a non work period throughtout barchart like you would achieve by using ’curtain’ function.

    Thanks once again
  3. 0
    Andrew Pearce ·
    If you want grahical enhancements like that then you need to buy Powerproject by Asta Developments.

    http://www.astadev.com/index.asp

    Not got the high power number crunching ability of Primavera but far better graphical output for use in general Construction projects