Duration Types

Nitin NaikMember for 21 years 8 months
Created
4
1
0
Hi,

Currently there are four Duration types which you can assign to an activity.

Apparently it works around the following equation -

Duration X Resource Units/Time = Units

I am looking for some real life examples to easily demonstrate different duration types and its use.

Please share your thoughts and examples on this topic.

Cheers

Nitin

4 replies

Oldest first
  1. 0
    Aydin Valiyev ·
    Hi Nitin,

    You can compare with P3 autocost rules. If you in P3
    1. Link RD to % complete it will give you in P5 duration type
    2. Unlink RD to % complete it will give you in P5 physical type

    I didn’t reach to Units yet.:)

    Cheers,
    Aydin
  2. 0
    Peter Nicol ·
    This might help explain things...

    The duration type affects the following 3 items:

    "Duration"
    "Units/Time"
    "Units"

    Whichever duration type you select will select which one of these 3 items change first. Each duration means the following:

    "Fixed Units/Time" - duration changes first and the "units" change 2nd. ie. if you change the duration of an activity, the units will change accordingly (based upon the units/time already set).

    "Fixed Duration & Units/Time" - "units" changes first and then duration changes 2nd.

    "Fixed Units" - duration changes first and units/time changes 2nd.

    "fixed duration and units" - units/time changes first and units changes 2nd.

    hope this makes sense

    -Pete
  3. 0
    Anoon Iimos ·
    it’s all linear! use only fixed units!
  4. 0
    John Murray ·
    Some example uses for the Duration Types…

    "Fixed Units/Time" – Use against a Level of Effort eg Project Manager over the duration of the Project.


    "Fixed Duration & Units/Time" – Typical Construction activity, remaining duration is forecast then this activity type gives the required units/resources per remaining time period (Projecting remaining required project resources to meet schedule), productivity may also need to be considered.


    "Fixed Units" – Use for High Level Schedule (perhaps Owners schedule or EPC study phase, Level 1, 2) to assist in determining the overall duration of a program by manually leveling (shrinking and stretching) activities to meet a perceived / achievable resource limit (base resource data is a high level estimate of resources).


    "fixed duration and units" - Typical Shutdown / Turnaround activity, when you want to know what it will take to make sure the work is completed on time, this good for re-assessing resource requirement (resource leveling) when a shutdown is in progress.

    Many arguments can be put for and against the above; however they are legitimate uses and would be best discussed with Primavera for your particular industry, also I have not looked, but I am sure many example exist on the Primavera Knowledge Base http://www.primavera.com/customer/index.asp

    Best Regards
    John