Total float

Rodrigo BrazilMember for 19 years 5 months
Created
2
1
0
Hi all,

Is there any way to keep the total float positive when you use "must finish by"?

Rodrigo

2 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Hi Rodrigo,

    Using Mandatory Finish as your constrain will remove your total float even you have float originally before constraining your activity. If you used mandatory finish dated earlier than schedule then you will have a negative float. This required changing your logic to override your negative float and change it back to 0 float.

    Regards,
    Rodel
  2. 0
    Kevin Button ·
    Be very careful when using a Mandatory constraint as it ignores all network logic.

    KB