Is there a quick way it import a WBS structure from an Excel spreadsheet?

2 replies

Oldest first
  1. 0
    Oliver Melling ·
    Check in the Help function under ’Modifying and importing data from an XLS file’.

    It tells you about mapping your headings in your xls spreadsheet with those found in P3e and also goes into more detail about importing from Excel spreadheets.
  2. 0
    Hamed Planner ·
    David as Oliver Said chek the Help , But also remember you need to have a superuser access in order to import an excel file , first try to do a sample wbs in Primavera then export it after copy paste your existing from excell in order to make sure it matches with coding and etc.

    good luck