Progress on baseline
In the Open Standard
Andrew PearceMember for 25 years 4 months
- Created
- 6
- 2
0
HELP Please!!!
I want to produce a layout that shows % complete bar on a baseline bar.
So far have been able to display baseline and % complete but % complete bar starts at actual start date not basedline start date.
It is a requirement of contract that this type of report is produced (Traditional dropline!)Only other way I can think of is to copy original programme enter actual start dates as planned start dates and not to reshedule plan.
I want to produce a layout that shows % complete bar on a baseline bar.
So far have been able to display baseline and % complete but % complete bar starts at actual start date not basedline start date.
It is a requirement of contract that this type of report is produced (Traditional dropline!)Only other way I can think of is to copy original programme enter actual start dates as planned start dates and not to reshedule plan.
6 replies
Oldest firstLog in or join to reply