P5 - Baseline Bars (not matching Start/Finish bars)
In the Open Standard
Roger PhilipMember for 19 years 4 months
- Created
- 7
- 3
0
Hi,
I am using Primavera Version 5.0.
I have been trying to re-baseline a schedule that is in progress but have had problems with activities that are either in-progress or 100% complete - the baseline dates being saved are not the same as the start/finish dates.
P.S. Baseline dates for actvities that are not started seem to working perfectly?
Any suggestions?
Thanks.
Roger.
I am using Primavera Version 5.0.
I have been trying to re-baseline a schedule that is in progress but have had problems with activities that are either in-progress or 100% complete - the baseline dates being saved are not the same as the start/finish dates.
P.S. Baseline dates for actvities that are not started seem to working perfectly?
Any suggestions?
Thanks.
Roger.
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?