Skip to content

What is the point of Planned Start and Planned Finish

Andrew LevittMember for 18 years
Created
26
10
0
For me the Planned Start and Planned Finish fields (and Original Duration) are nothing but a nuisance. I have to constantly run a global change to overwrite them with the Start and Finish fields in order to use Apply Actuals or Update Progress without mucking up any changes I’ve made. I understand how to avoid making my life difficult with these fields, but I don’t understand how to make my life easier: what’s the point of having them? I have a baseline to compare the current schedule against, so why have this intermediate fake baseline? And even if it were a good idea to have an intermediate baseline, WHY ON EARTH DOES IT OVERWRITE MY SCHEDULE WHEN I RUN APPLY ACTUALS? Primavera is written by a great team so I’m sure they had something in mind...

26 replies

Oldest first
  1. 0
    Omar Grant ·
    Hi Andrew - I think the Planned/Finish dates are a bit like an ’expected’ start/finish and the Help says it allows the ’Project Manager’ to manually put schedule dates in!! How dangerous is that!

    cheers,

    Omar
  2. 0
    Anoon Iimos ·
    I believe Planned Start, Planned Finish, and Original Duration are only intended for Baseline Schedules.

  3. 0
    Ronald Winter ·
    Andrew, you have asked a better question than you know. The purpose for Planned Dates? Why to drive the placement of the bars in the Gantt Chart, of course! Every time you look at the bars, you are seeing what the planned dates say.

    Try changing the planned dates and watch the Early Start/Finish columns stay the same while the Start and Finish columns change and the bar moves to the new Planned Dates. Change the Start/Finish date and the Planned dates and the bars do not change.

    Don’t you just love how good Primavera explains all of this? Good question!
  4. 0
    Andrew Levitt ·
    Ronald:

    You’re right that the Planned dates for unstarted activities are the same as the dates used for Gantt bars, but I would argue that the Gantt bars are based on the Start/Finish pair rather than the Planned’s.

    When an activity is In Progress or Complete then the Planned dates no longer impact the Gantt chart nor the Start/Finish pair--the Gantt shows the Start, and the Start is reflective of the Actual Start Date. The Gantt also shows the Finish, which for an In Progress activity is the Early Finish, and for Complete activities is the Actual Finish.

    For both In Progress and Complete activities the Planned dates are essentially no longer relevant, except (for me) for the hateful fact that Apply Actuals and Update Progress will overwrite the Actuals or even change the Rem. Duration in order to match the Start/Finish to the Planned’s.

    Which brings me back to my question--what’s the point of the Planned’s?
  5. 0
    Anoon Iimos ·
    Andrew,

    I guess the problem will come in when you do the automatic updating (apply actuals / update progress automatically) which I believe that you should never do it in your Current/Updated Schedule (you can only use it in your Baseline Schedule - to see if where you’re supposed to be at a certain time).

    Of course Planned Dates are relevant, especially when you do the comparison.

    You did not specify whether the Planned Dates you’re referring to are Early or Late by the way..?
  6. 0
    Paul Harris ·
    I agree the “Planned Dates” are a disaster.

    Most people do not even know that these dates even exist net alone where how they are calculated or how they are used or when! The Primavera documentation does not give a clear indication of what they do or how they calculate.

    They are very complex but basically:
    1. When an activity is complete or in progress they are set to equal to the last update, say similar to the last periods status.
    2. When an activity is unstarted they are set to the early start and early finish. There is a whole page of documentation in my book on how they calculate but it is all a bit academic as any normal scheduler would never want to display them or any data that is associated with them.

    I have found the Planned Dates are used in:

    1. Progress Spotlight, so one does not get the expected result as one would with P3, SureTrak or MPS with update progress. You will find that Actual dates are changed for you to the Planned Dates without telling you! To overcome this problem you may run a Global Change to set them equal to the Start and Finish dates first.
    2. When a Baseline has not been assigned they are used to display a Project or User Primary Baseline bar. This is because the Planned dates are represented as bars when the is selected in the Assign Baselines form.. This opens up a raft of issues with multiple users using the same Layout. Thus when one user assigns a Primary User Baseline and a second user applies this layout but they have not assigned a User Baseline the "Planned Dates" are used as a Baseline.
    3. They are also used in the Activity Usage Profile to show the Budgeted values (term confusion again) and as the Baseline values when no baseline has been set. Once a Baseline has been set they use the Baseline dates.
    4. They are also used in the Activity Usage Profile to show the Earned Values curves when no Baseline has been set. Once a Baseline has been set they use the Baseline values to display the Earned Values curves.

    So in summary Planned Dates do not always display Planned information. They are used to display Budgeted and Current information as well. An unfortunately if you have not set a Baseline then the Planned dates will be used to display data you probably do not want displayed.

    You have to be very careful with what you do with this software and make sure you have tested all your options before you start using it, so you are sure it is displaying what you think it should. It is a high risk software as things are not always what they seem to be or what they are called by the software. I am looking forward to some meaty legal cases with some mix ups that will eventuate from a misunderstanding on how the software works.

    I would prefer the Planned dates to be removed from the system all together and data such as Baseline Bars and Curves should not display any data if a baseline has not been set. I would go even further to say that I would also like Budgeted values to be removed from the Current Schedule resource assignments (which is not always the Current Schedule as the Current Schedule baseline is actually the Planned dates) and only exist in a Baseline and thus remove another source of confusion which appears to have been inherited from P3.

    I am glad I have retired from scheduling and now spend most of my time trying to teach people how to use this software.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
    www.eh.com.au
  7. 0
    Andrew Levitt ·
    Paul,

    I couldn’t agree with you more, it is critical to understand the behavior of the Planned dates. If anyone needs any help understanding the behavior of the Planned dates beyond what Paul has outlined in his post, there is an excellent explanation with illustrations and exercises in the best Primavera reference book around, Project Planning and Control, by the very same Paul Harris.

    So I haven’t heard any posts saying how those Planned dates can be useful, so I’m going to go ahead and say that they are a botched attempt at getting people who don’t save baselines to have some sort of quasi-baseline anyway, and that the behavior with respect to Apply Actuals and Update Progress resulted either from bad judgment on the part of a product developer or some sort of horrible miscommunication. The workaround is to run a Global Change every single time you use Apply Actuals or Update Progress.

    Now that my curiosity is piqued I’m going to try to track down the Primavera product guys and see what they have to say.

    Andrew
  8. 0
    Armando Moriles ·
    Hi Paul,

    MY QUEST FOR THE EARLY AND LATE CURVES IN THE ACTIVITY USAGE PROFILE...

    I exported to excel my working programme planned dates and my baseline late dates. Then I replaced my working programme planned dates with the baseline late dates. After that, I imported my working programme back.

    When I checked my working programme activity usage profile, I was surprised because the budgeted and baseline curves becomes equal.

    I was really expecting that the budgeted curve would become my baseline late curve.

    It appeared to me that the baseline in the activity usage profile is actually a late curve and not early.

    Any help will be highly appreciated...

    Thanks,

    Arman



  9. 0
    Armando Moriles ·
    Paul,


    I apologize in my previous question as I forgot to restore my baseline that’s why the budgeted and baseline curves in the activity usage profile becomes equal.

    As I restored my baseline, the budgeted is almost the same with the remaining but still the completion date is beyond the baseline date which means that the budgeted curve is still not the baseline late curve even if i already replaced the planned finish date with the baseline late date. I’m still hoping and looking forward in knowing the solution or way how to show the baseline early and late curves in the activity usage profile. Is there?

    Thanks,

    Arman
  10. 0
    Anoon Iimos ·
    On the contrary, i don’t really think that "Planned Dates" is a disaster. I believe this separates the Baseline and the Current Schedules. So if it happens that you don’t understand what’s the difference between a Baseline and a Current Schedule, i believe there is a Paul Harris that is willing to teach.
  11. 0
    Andrew Levitt ·
    Anoon:

    I couldn’t understand your post, but I’m hoping that you know something about the usefulness of the Planned Dates that I might be missing. First of all when you say Current Schedule do you mean Early Start/Finish? And when you say Baseline Schedule I think it’s fair to assume you mean BL Start/BL Finish or some other frozen baseline somewhere.

    So how do the Planned Start/Planned Finish come into play for you? These are not frozen like the baseline, nor are they dynamic like the Early schedule. And do you use Apply Actuals or Update Progress? Don’t you find it irritating that those tools overwrite your Actual Start/Actual Finish with whatever values happen to be in the Planned Start/Planned Finish fields? I mean the last thing *I* would ever think to do is overwrite actuals with anything even remotely like a baseline, otherwise at the end it looks like everything happened according to the original baseline plan and you can’t derive any lessons learned or come up with more accurate estimates.

    Thanks for any comments.

    Andrew
  12. 0
    Mark Chapman ·
    Well done Andrew. I totally agree with you. Please add me to back up your claims of aggrieved users. Don’t I hate it when the planned finish overwrites my actuals.
  13. 0
    Anoon Iimos ·
    Andrew,

    I agree, Baseline Schedules are supposed to be frozen (with regards to dates). When I say Current Schedule - this is supposed to be your working schedule which is dynamic, has early and late dates, and yes (what I believe) has Planned Dates (which is supposed to be your forecast dates). I’m only talking for myself by the way, I’m not really sure if it is how the program was designed for (anyway I believe that you solicit my opinion).

    Apply Actuals or Update Progress Automatically (or using progress spotlight) - to be honest, I only use it in my Baseline Schedule (to reflect the forecast progress as originally planned at a certain time). I never use it in the Current Schedule. Why? in my experience, I never encountered a schedule that really happened as planned.

    So in principle, the point of "Planned Dates" is self explanatory (why you need a Plan?). But how it functions in the program (software) is I guess will depend on the user.

    cheers
  14. 0
    A D ·
    Paul and Anoon, both have said it correctly and certainly it is not at all required in P6. It will be helpful, only if u need to update few selected activities.

    It will be useful only if u can provide planned start and planned finish dates for say, a group of activities and then go to Tools --> Update Progress and their u have an option wherein u can update only selected activities.

    Or otherwise Planned dates are not at all required in P6.

    Similarly, as asked in previous thread, we dont require Anticipated Start and Anticipated Finsih dates. We can have anticipated bars only in WBS view and not in Activity chart. If v are not certain of few WBS Elements, then we can have anticipated dates in WBS form but cannot be displayed in activity chart. So, whats d fun of having these type of dates??
  15. 0
    David Kelly ·
    Couple of extra "gotchas" that Planned Start and Finish have in store for the unwary. Over and above Paul Hariis’s list:

    When you use a baseline its the Planned Start and Finish from the baseline plan that are the dates primavera uses. Now this is fine if the Baseline was taken before there was any progress, or has never been updated, but there are issues if you need Actual dates from the baseline.


    Auto Compute Actuals works on Planned dates for expenses and (I think) resources.


  16. 0
    Anoon Iimos ·
    Armando,

    I believe that you mixed up the "Planned Dates" of your Baseline and your Current Schedules. I suggest that you treat the schedules (baseline vs. current) separately. Planned Dates for Baseline (early and late) are different from Planned Dates (early and late) of your working or current schedule (assuming that you had already made updates), so the remaining values might be different.

    David,

    What do you mean? A Baseline Plan that has actuals? And you schedule the remaining works as your Current?

    I believe that "auto compute actuals" works only for Baselines (which are not really actuals but planned actuals). So why use it in your Current or working schedule?

    cheers

    p.s. Ravi, I never said that "Planned Dates" are not required in P6. (maybe before when I was still trying to learn) but as I go mature (i hope i did), I believe it is.
  17. 0
    A D ·
    David,

    If u r having actual dates, in ur baseline program, and if u select planned dates for earned value calculation, then it may show wrong dates.

    Go to Admin --> Admin preferences and then go to Earned Value Tab. At the bottom, u can find option for calculating earned value from baseline use:

    - Budgeted value with planned dates
    - Current Dates
    - XXX (Check)

    U need to select current date option, if u hav actual dates in ur program or the other option is to run Global Change.

    Cheers,

    Rav
  18. 0
    Andrew Levitt ·
    Anoon:

    Looks like you keep your baseline in a separate project, which is great but by no means universal. You can also keep a baseline within a project itself in the BL fields. In which case it doesn’t make sense to talk about a baseline’s Planned dates, nor does it make sense to talked about updating the baseline. Which I’m curious about--why would you perform auto compute actuals on a baseline? I use auto compute actuals so that I can move the Data Date without having to manual recompute the percent complete on every activity; instead I just make sure the finish date is correct, run a global change so the Planned Dates don’t screw everything up, and then run Auto Compute Actuals to move the Data Date.

    Andrew
  19. 0
    Anoon Iimos ·
    Andrew,

    When I was 12 or 13 years old, I’m doing manual labor (making CHB manually), so I would say that my background is construction. Until now, I never really give a d**n about how this software/programs work (I’m not a teacher, I’m a construction worker), I just need a Construction Plan.

    And I would like to reiterate that for me, Auto-compute Actuals or Update Progress Automatically, are only applicable (or only good) for Baseline or Target Schedules (If I am wrong or you got different opinion, so be it, I respect it).

    Please don’t forget to inform me if you found later (proven and tested) whether or not I’m right.

    cheers
  20. 0
    Bilal Ashraf ·

    Hi,I am a beginner in P6, Can

    Hi,

    I am a beginner in P6, Can somebody please help me for a problem that, I have imported XER file and i want to change BL Finish date for the whole project, I have reduced the durations for each activity and BL Start Finish Dates but BL Finish date for the entire project remains the same, why is that happening ? Is there any constraint I am facing ?

    Please help me

  21. 0
    Zoltan Palffy ·

    Bilalcreat a new post do not

    Bilal

    creat a new post do not glam on to someone elses thread

  22. 0
    Bradley Gibbs ·

    I realise this is an old

    I realise this is an old thread, but the existence of planned dates has me perplexed for many years.

    When a baseline is assigned to a programme, the baseline start/finish fields display the planned start/planned finish from the baseline programme which may be different to the start/finish dates in the baseline programme. Right?

    I frequently overwrite the planned start/finish with start/finish using a global change,  but when I need to explain this issue and procedure to clients or employers they generally find it unbelievable.

    Why on earth was this not resolved years ago?

     

     

  23. 0
    Rodel Marasigan ·

    Planned Date is a very useful

    Planned Date is a very useful date in Primavera for current live project that you are updating. It is the original date that Project Schedule has been set / calculated during the creation of Project Schedule. If the Project schedule is saved as Project baseline before the update and assigned, then the Planned date and baseline date should be the same before the update. Please note that Baseline date is different from project planned date. The planned date is the calculated date by Primavera based on logic and or constrained set to activity to start or finished and can be override or change manually by the scheduler or Primavera user during the update. The behaviour of the planned date is depending on the project calculation settings during the update. If the "link Budget and At Completion for not started activities" is not tick, then any changes to remaining duration or At Completion duration or changes to finish date will not affect original duration and or Planned Finished date for not started activities. It tick is selected any changes to remaining duration and or At Completion duration or Planned Finish date will synchronise to original duration for not started activities.

    The planned date is useful to compare the current live project planned vs actual as live and not as baseline. Very useful when creating a what-if scenario of current live project planned vs actual vs baseline.

    Very useful to compare the current project forecast planned vs forecast remaining if “link Budget and At Completion for not started activities" is not tick.

  24. 0
    Bradley Gibbs ·

    Hi RodelI am not sure what

    Hi Rodel

    I am not sure what you mean by “Baseline date is different from project planned date” as it is my understanding that when a user displays a baseline date it will reflect the planned date if the the baseline is set as current project.  I also understand that current start/finish dates are different from planned start/finish dates, as this is precisely what I take issue with.

    I respectfully disagree with your statement “Planned Date is a very useful date in Primavera for current live project that you are updating”. In my opinion there should be no reason that a user wanting to compare current dates with dates from a previous update should not simply be able to take a baseline and assign it.

    I can see you have commented on the following post by  Yaser A. Al-Bustanji

    http://www.planningplanet.com/blog/understanding-planned-dates-oracle-primavera-p6

    which includes these statements:

    • “In my experience, the stored data in the planned date fields is of no importance at least in the construction industry. This is also the case in other industries if we know that the Planned dates may hold a completely irrelevant data”
    • “This leads to a situation in which the Planned dates store irrelevant and misrepresented information that should never be displayed or used for any purpose”
    • “The Planned dates of the baselines assigned to the current schedule are used to display the relative baselines bars. This option applied by default as the Earned Value Calculation tab under Admin, Admin Preferences tab is set to “Budgeted values with planned dates”. This is a very confusing option especially when a progressed schedule is being used as baseline because the baseline bar are displaying irrelevant data (Planned dates). It is recommended that the user should use the "At Completion values with current dates" or “Budgeted values with current dates” under “Earned Value Calculation” tab under Admin, Admin Preferences tab as per figure (17) to display the correct baselines bars.”
    • “The data stored in the Planned date fields is of no importance. It is not help in any way in the schedule analysis and/or reporting purposes as they may hold irrelevant data.”
    • “The process of updating schedule will affects the Planned dates fields; if the user calculates the schedule and then set the actuals, this will lead to completely irrelevant data being stored in the Planned dates fields.”

    My requirement is very simple - I want to compare the start/finish dates between two updates provided as .xers from the client. Fortunately, the solution also appears to be quite simple, as per the above recommendation: change the default earned value calculation setting in admin preferences, i.e. do not use Budgeted values with planned dates.

    Regards

    Brad

  25. 0
    Rafael Davila ·

    https://www.ronwinterconsulti

    https://www.ronwinterconsulting.com/Understanding_P6_Dates.pdf

    So how do the planned start/planned finish dates come into play for you? These are not static like the baseline, nor are they dynamic like early dates. They are involved if you use Apply Actuals or Update Progress. The user can change the planned dates as desired. If there is no baseline assigned, then the planned dates are used for calculating the variances. Planned dates also
    have the potential to overwrite your actual start/actual finish with the planned start/planned finish dates. It is a highly suspect feature that automatically overwrites actual dates. Once done, everything looks like it occurred according to the original baseline plan.

    • If not well documented should not be shown.
    • If can inadvertently override actual dates then they are flawed.

     
  26. 0
    Rodel Marasigan ·

    Hi Brad,If you read my

    Hi Brad,

    If you read my comment on the post by  Yaser A. Al-Bustanji, you should already understand what is planned date. No offense to Yaser but he had a very minimal understanding of how P6 works and what is planned dates is all about.
     

    Like what I have mentioned, Planned date is different from Baseline date. Planned date is the original date that has been calculated by the software based on logic and or constrained during development of the schedule. It will the result after running the schedule calculation (F9) before and after the update of the current live schedule. Depending on the settings selected the behaviour of Planned date when calculated for non-started activities. Planned date is static and can be altered or modify by the user. Planned date can be used for calculating variance if no baseline assigned for current project.

    Baseline is a copy of the current project maintained and assigned to the current project. Baseline cannot be altered or modify compared to Planned date unless baseline is removed and restored to modify.

    Planned date is very useful when running the what if scenario on history of original date and its movement such as schedule planned analysis and forensic scheduling. It also involves using the feature of apply actual or update progress.

    If you only wanted to compare the update schedule on weekly variance (i.e. weekly update and made copy of current for previous week comparison) then you have to change the settings of Earned Value using current date and At completion because you are comparing current date and not planned date.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?