Skip to content

limited licensed activities in p3 contractor

Mark JohnsonMember for 19 years 9 months
Created
1
1
0
hi i came across this brick wall while importing into an epc schedule is there any way around it..having unlimited import activites

1 reply

Oldest first
  1. 0
    Arthur Godbeer ·
    If you’re asking about limitations on the number of activities in Contractor, then by design Standard is a max of 750 per project and Deluxe is 2000. Project Management in the Planner/Scheduler s/w is unlimited.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?