Cost all n 1

Hady Shendy, PMPMember for 20 years 4 months
Created
1
3
0
Hi All
I have some activities with expense cost for each activity,
How can I create one activity include a total of expense costs for above activities?
I.e. Activity A cost $100,
Activity B cost $150,
Activity C cost $550,
Activity D is sum of activities A,B&C which automatically its cost $800

Regards

1 reply

Oldest first
  1. 0
    David Kelly ·
    We don’t do summary activities in P5. That’s a disease microsoft proiject has. You need a code structure e.g. the WBS or any activity code. Summarisation by code is Primavera’s "crown jewels", you should aim to have all your activities at the same level and as many code structures as everybody needs to summarise. No "dummy" acvtivities.

Log in or join to reply