Skip to content

Performance % Complete

Niles LuoMember for 20 years 10 months
Created
8
2
0
Dear all:
Can anybody give me some suggestion about how to calculate the value of ’Performance % Complet’ for an activity or a project in P3ec. Thanks a lot

8 replies

Oldest first
  1. 0
    Steven Oliver ·
    Define your interpretation of "Performance"
  2. 0
    Manoj Singh ·
    Earned Value Measurement System (EVMS) is a rational method for Measuring Performance that can help the Project Teams manage their work more effectively by:-

    1)Anticipating problems before they become acute
    2)Using factual data to understand what is happening
    3)Recognizing trends and correcting them
    4)Applying lessons learned to improve future performance
    5)Preventing Margin Slippage.


    Here Are The Earned Value Terminology:-

    BCWS = Budgeted Cost of Work Scheduled=Planned Value
    BCWP = Budgeted Cost of Work Performed=Earned Value
    ACWP = Actual Cost of Work Performed= Time Charged
    Schedule Variance = BCWP-BCWP
    Cost Variance = BCWP-ACWP
    Schedule Performance Index (PI) = (BCWP/ACWP)
    CostPerformance Index (SI) = (BCWP/BCWS)

    Hope i am clear.
  3. 0
    Steven Oliver ·
    Which, whilst correct, doesnt address the original question.
  4. 0
    Raed Hussein ·
    display the WBS Window and click the earned value tab

    choose the technique for computing the performance % complete

    which is consider to calculate earned value

    earned value = budget at completion * performance % complete
  5. 0
    Raed Hussein ·
    I would like to correct the following

    Schedule Variance = BCWP-BCWS
    Cost Variance = BCWP-ACWP
    Schedule Performance Index (SPI) = (BCWP/ACWS)
    CostPerformance Index (CPI) = (BCWP/ACWP)
  6. 0
    Frank Neal ·
    SPI = BCWP/BCWS.....not ACWS..this does not exist!
  7. 0
    Dinesh Kumar Damavarapu ·
    Hi Niles Luo,

    Performance % complete is the earned value of any activity.Earned value can be based on quantities, cost mhrs etc.

    In P3e if you are using performance % complete, it is better to base on the cost in updating the activity % percentage complete as P3e only uses cost in summarising the percentage at different WBS or activity code level.

    I hope it clarifies.

    Cheers.

    Dinesh
  8. 0
    Alex Wong ·
    Hi

    If you using Performance % Complete as well as Steps
    your % complete will base on your step completion

    If you only using performance % comp then it is a value entre by you of your estimated completion of the activity

    HTH

    Alex

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?