Project Managemnet- Primaver 5.0

Raed HusseinMember for 19 years 4 months
Created
6
3
0
gantt chart is not displayed in project window, could anyone comment on why and how?

6 replies

Oldest first
  1. 0
    Steven Oliver ·
    What is shown ?
  2. 0
    Raed Hussein ·
    only table is shown
  3. 0
    Niles Luo ·
    Maybe you forget to click the Gantt Chart button.
  4. 0
    James Skelton ·
    check you timescale start & timescale finish in page setup option tab. I have found that if the timescale is not set for your projects approximate start & finish then the gantt will not show
  5. 0
    Raed Hussein ·
    thank you mr/ james skelton you solve my problem
  6. 0
    Marcio Sampaio ·
    Chek Primavera windows divider.

Log in or join to reply