Hello Planners,

Can you please advise me.... whether it is possible to put the time scale at the bottom of the layout in addition to the top one?

Appreciate your inputs. Thanks
Imam Baig

6 replies

Oldest first
  1. 0
    Ashraf Jahangeer ·
    Hi Imam,

    It is possible to print the schedule with timescale in the bottom.

    Command sequence is as follows.

    File -> Page Setup -> Timescale Placement -> Select Bottom.


    Regards,


    Ashraf
  2. 0
    Andrew Pearce ·
    Sorry guys,
    Perhaps I am having a Senior moment but in P3e I cannot find that option in page set up menu
  3. 0
    A D ·
    Sorry Imam,

    I dont think so, there is any such option in Primavera 3.1
  4. 0
    A D ·
    I mean to say, while working in Primavera 3.1, there is no such option, yaa but in page set-up, yes there is an option, and you can see the same in print preview only.

    Cheers,

    Raviraj
  5. 0
    Mirza Imam Baig ·
    Thankx for your inputs.

    Yeah, it’s possible in P3-3.1. But my question is for P5? Whether this option is still available for P5???
    Please advise. Thanks
  6. 0
    Frank Borcherdt ·
    Not in P5 and nothing in Version 6 beta notes to indicate this is coming.