Time Distributed curve
In the Open Standard
SR
Shiv RaoMember for 18 years 7 months
- Created
- 28
- 5
0
28 replies
Oldest first- 0DWDieter Wambach ·I don’t know how long you sat already.
1. m3: Material is a resource. You can enter the budgeted quantity, P6 will then calculate the qty per day based on the duration. For the percentage you can use a UDF and a calculator or Global Change
2. Cash flow is related to money. Price per m3 will give the figure per month to you. For material resources histograms and curves are displayed for costs, not for the physical quantities. It is a requirement for an add-on from some German companies to Primavera.
3. Resources: See resource usage profile or -Spreadsheet
- 0SNSatya Narayana ·"I don’t know how long you sat already. "
What does this mean.
The feature i was asking was already in P3 and i have used it a lot for presenting things to higher management who understand percentages.
coming to the calculator can we use the formulas as we use in spread sheets in P6??
- 0AWAlex Wong ·Hey PPs
Don’t export it out
its very very simple - all you need is some basic maths knowledge
Using the same example
Total plan quantity is says 15,000 m3
then all you need to do is to use
the resource usage profile, resource usage profile option,- Graph, tick the "calculate average" and Divide the total by 150 (% = Accumulated value / 15,000 * 100%) and change the symbol to %
Done
Simple
Alex
- 0AWAlex Wong ·and beside you only have 2 decial points you can display in P6
it becomes pointless to be accurate down to 6 decimal point
Your management team need to be a bean counter to be so accurate.
Well Project Management is never about pin point accuracy, its about how to manage the info to give the best possible outcome
Good Luck
Al - 0SNSatya Narayana ·Thank you, U r right.
I was wrongly thinking it shall allow only up to 999,999 but we can go up to 99 million, though the project cost is in billions we can just keep at as billion of currency.
It works.
Coming to the question again, can i export the activity and reosurce usage spead sheet directly to excel without going to reports. can we show the values on the curves and histograms?? - 0AWAlex Wong ·Arnold
Dont understand, U can directly copy and paste from the "ASSIGMENT" screen, In addition you can display format / unit ... what ever you like in the scale.
Unless we are using a different software, I believe this is rather simply to do what you are asking for.
Good Luck
Alex - 0APArnold Puy ·Alex,
Yes you are right! We can easily Copy & Paste the "RESOURCE ASSIGNMENT" to excel. however, we are talking about the Activity & Resource Usage Spreadsheet according to Mr. Sad’s question.
If there is a way to Export directly to Excel for Activity & Resource Usage without generating Reports then, perhaps you can share to us if HOW to do it? For showing the Values of Curves & Histograms, I think this features is not supported by P6.
Regards,
Arnold
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?