Time Phase Budget Data
In the Open Standard
Hasan Atif BilgramiMember for 22 years 7 months
- Created
- 1
- 2
0
Hello Every one.I would be grateful if somebody help me.
I generated a Time phased Budget in P3e from Jan 07-July 07 of an activity called Finishing works (just an example).
Then i run report in csv format in order to get Time Phase Budget figures.
I sit with my Commercial Manager to see whether this P3e generated budget is realistic or not.
My commercial manager did some changes on that time phased budget ( Please note that the total Budget value is remains same,only the time phasing budget values changed)
Now, my Commercial Manager wants me to do Is to import these new time phased Budget values into P3e and then Baseline it or freeze it in order to make it Performance Measurement Baseline.
I have tried to import it to failed.
Please help me
Regards
Has
I generated a Time phased Budget in P3e from Jan 07-July 07 of an activity called Finishing works (just an example).
Then i run report in csv format in order to get Time Phase Budget figures.
I sit with my Commercial Manager to see whether this P3e generated budget is realistic or not.
My commercial manager did some changes on that time phased budget ( Please note that the total Budget value is remains same,only the time phasing budget values changed)
Now, my Commercial Manager wants me to do Is to import these new time phased Budget values into P3e and then Baseline it or freeze it in order to make it Performance Measurement Baseline.
I have tried to import it to failed.
Please help me
Regards
Has
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?