Actuals on Resource useage profile graphs
In the Open Standard
Minhas ShaikhMember for 19 years 6 months
- Created
- 3
- 2
0
Hi Planners,
I have a problem for resource useage profile.
After assigning resource budgeted and actual units . In resource usage profile graph, it shows budgeted , remaining unit curves only not "actual units curve". if we double click on graph it will give all values of budgeted, remaining as well as actuals .
I also click on "resource usage profile options" and all are allowed to show.
Can anybody help me solve this problem.
Minhas
I have a problem for resource useage profile.
After assigning resource budgeted and actual units . In resource usage profile graph, it shows budgeted , remaining unit curves only not "actual units curve". if we double click on graph it will give all values of budgeted, remaining as well as actuals .
I also click on "resource usage profile options" and all are allowed to show.
Can anybody help me solve this problem.
Minhas
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?