Actuals on Resource useage profile graphs

Minhas ShaikhMember for 19 years 6 months
Created
3
2
0
Hi Planners,
I have a problem for resource useage profile.

After assigning resource budgeted and actual units . In resource usage profile graph, it shows budgeted , remaining unit curves only not "actual units curve". if we double click on graph it will give all values of budgeted, remaining as well as actuals .
I also click on "resource usage profile options" and all are allowed to show.

Can anybody help me solve this problem.

Minhas

3 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Minhas,

    Right click your graph area and select Profile Settings then tick the actual cumulative tick box. That should show your actual curves.

    HTH
    Rodel
  2. 0
    Patricia Le Clainche ·
    Minhas,

    Do you systematically have the pb or is it from tile to time ?

    I met some problems like your in Resources Profile Graph in Activities View. I think it was due to a wrong choice of StartUp Filters (in User Preferences).

    Maybe someone else met such troubles ?
  3. 0
    Minhas Shaikh ·
    Thanks for everybody.. I solved my problem.