Calculating Duration of Summary Tasks

Ijaz AhmadMember for 20 years 3 months
Created
2
2
0
Hi guys!
I am finding trouble to customize the duration setting for summary tasks in P5. What I am seeing is that P5 calculates the duration of summary tasks based on calender 5days x 8 hrs/day. How can I change this setting?

2 replies

Oldest first
  1. 0
    Andrew Podolny ·
    The duration of summary task are calculated based on Default calendar. To change it go to Enterprise-->Calendars... and
    change the Default calendar by checking the box.

    Regards,
    Andrew
  2. 0
    Ijaz Ahmad ·
    Thanks Andrew