Importing from P3 to P5

Dev TamboliMember for 19 years 4 months
Created
1
1
0
when i tried to import programme from P3 to P5, activity codes disappeared so i cant organise the programme, i checked several times but same problem encountered.

Experts, please suggest.

Dev

1 reply

Oldest first
  1. 0
    Dieter Wambach ·
    Hi Dev
    There is aparameter in the import procedure. If you select "Combine subproject" the activity codes will be imported as project activity codes. Otherwise as global.