’Secondary’ Role
In the Open Standard
Philip RichardsMember for 22 years 9 months
- Created
- 1
- 3
0
How can I get the Role Profile Histograme to recognise resources which are available, but have the particular role allocated as a secondary as opposed to Primary.
ie Engineers available are as follows:
Engineer 1 Primary Role = Detail Engineer
Engineer 2 Primary Role = Detail Engineer
Engineer 3 Primary Role = Checker, but Secondary Role = Detail Engineer.
Requirement is for 3 Detail engineers, but Role profile shows 2 available, and overload of 1.
ie Engineers available are as follows:
Engineer 1 Primary Role = Detail Engineer
Engineer 2 Primary Role = Detail Engineer
Engineer 3 Primary Role = Checker, but Secondary Role = Detail Engineer.
Requirement is for 3 Detail engineers, but Role profile shows 2 available, and overload of 1.
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?