Skip to content

Resource assignment doubling.!

Frank NealMember for 23 years 8 months
Created
0
2
0
When updating P5 with P3 data the resource assignments are doubling.!

any advice would be appreciated.

We also are unchecking the box..."Resources can be assigned to the same activity more than once"...but after each import, the box is rechecked.

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?