Zameer JeffMember for 19 years 5 months
Created
1
1
0
Thanks colleagues for your help in past. I could not say thanks individualy but I got great help from you and i acknowledge that.

My recent issue is updating activities which start and then stop without finishing, then they start at another point of time and stop again without finishing and now i am expecting them to be started again in next week.
Please let me know how to break down them into different intervals of time, or any other way of handling them.

Please give answer in detail or in steps.

Thanks

1 reply

Oldest first
  1. 0
    Alex Wong ·
    Zameer

    there are sereval way to achieve the start and stop

    1. Constraint - Supspend and Resume - when you update the schedule then you can either select what date is supspended or resumed. This is useful if you dont know when the activity is stopped

    2. Calendar - you can create a specific calendar for this activity so that you can planned which time period will be non working and which is working. This is useful if you have several known stoppage

    3. use combination of 1 and 2

    Good Luck

    Alex