RESOURCE LEVELLING

Paul WaterMember for 19 years 4 months
Created
1
2
0
For resource change from one set of activities to another set of activities I started from resource usage spreadsheet, current project resource, then sorted by Resource ID, in the current project set the actuals 0 and fill down 0 for the current project’s set of activities. Can anyone please write me the steps for resource changes from one set of activities to another? I am missing some step?

1 reply

Oldest first
  1. 0
    Niek Zonneveld ·
    Paul,

    Have you considered using global change for this?

    Furthermore a note of caution. Be aware that you need to treat in-progress activities differently than non-started activities,

    HTH