Gentlemen.........Need some help...

1- How primary resource determine / created for imported file from P3.1.

2- How to force a resource to become a primary resource from imported p3 file.

1 reply

Oldest first
  1. 0
    Ronald Winter ·
    Primary Resource does not mean what you think it does. It is assigned by thE Administrator to a task and designates the person who is able to automatically update the percent complete of the activity through timecards.

    You may be confusing primary resource with "Controlling Resource." Good luck!