Hi All

Finally getting the hang of this P3e applicatiion! Can anyone help and put me on the path to exporting Timephased BCWP + BCWS to a csv file? I know how to export etc however I am having paticular problems with these 2 items (I have been a junior planner for a month and its the first time I have been asked for this information.


Thanks in advance :0)

2 replies

Oldest first
  1. 0
    Niek Zonneveld ·
    Kenny,

    You’ll need to export that data through a report.

    Just generate a report with the wizard - choose time distributed data and select activities as subject area - select the earned value fields you want print and the interval size, and generate ASCII output with the delimiter you desire.

    HTH
  2. 0
    Kenny Holmes ·
    Thanks, figured it out today :0) realised all fields are available however you need to look for them! Thanks again!