Stored Period Performance
In the Open Standard
Robin KilmisterMember for 19 years 6 months
- Created
- 1
- 2
0
Hello Planners,
I am transferring my projects from my local PMDB to a central server based PMDB.
I have noticed that all of my previous ’stored period performances’ have been rolled up into one overall ’actual labour units’ value.
Is there a way to extract the previously ’stored period performance’ information as loggeed on the local PMDB in the newly imported central server PMDB project?
Many thanks for your assistance.
Robin.
I am transferring my projects from my local PMDB to a central server based PMDB.
I have noticed that all of my previous ’stored period performances’ have been rolled up into one overall ’actual labour units’ value.
Is there a way to extract the previously ’stored period performance’ information as loggeed on the local PMDB in the newly imported central server PMDB project?
Many thanks for your assistance.
Robin.
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?