Importing from P3.

Dattatreya PadharthiMember for 23 years 6 months
Created
3
2
0
Dear All,

i am unable to import one of the P3 projects, the error shown is "Project Conversion failed, Unhandled exception occured"., Surprisingly all other projects (APEx, BASE etc)are successfully imported.
Can some one enlighten me on the solution to this problem or are there some restrictions while importing from P3.

Thanks in advance
Dattatreya

3 replies

Oldest first
  1. 0
    A D ·
    Hi Datta,

    Check the planning Units. Its days or weeks or hours?
  2. 0
    Dattatreya Padharthi ·
    Hi Ravi,

    Checked the planning units, its same.

    Datta
  3. 0
    Dieter Wambach ·
    Hi

    in the template for the import there is a parameter "include unused WBS". Switch it off and try again. In many cases this worked.

    If not, ask again.

    Regards
    Dieter