Resource Issues

Minhas ShaikhMember for 19 years 6 months
Created
2
1
0
Hi Planners,
In P3e I have assigned resources on given activities. Resource units are labour and material. Most of atvities are linked togather. But One activity creates a huge lag. if I remove resouce from that activity then automatically lag removes. I don’t know where from that lag comes. I need to assign resource on that activity.That activity repeats many times in my schedule.

(2)for checking of resources in resource usage graph I don’t see any unit . It gives zero in total and commulative although activity had been started. or it gives after finishing of activity.

If any body know the solution please reply.

Minhas

2 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Hi Minhas

    It seems that your activities are resource driven - activity type: resource dependent and the associated calendar has some holidays or in the master data under "Units & Prices" the maximum units are set to 0.

    Regards
    Dieter
  2. 0
    Khuong Do ·
    Hi Minhas

    For second query, the reason you can not see resource graph is unit conflict between labour(hour) and material(e.g feet long)
    If a diagram have 2 kind of resource,which have different unit measure, it can not be drawn.

    Thanks
    Khuong