Resource Issues
In the Open Standard
Minhas ShaikhMember for 19 years 6 months
- Created
- 2
- 1
0
Hi Planners,
In P3e I have assigned resources on given activities. Resource units are labour and material. Most of atvities are linked togather. But One activity creates a huge lag. if I remove resouce from that activity then automatically lag removes. I don’t know where from that lag comes. I need to assign resource on that activity.That activity repeats many times in my schedule.
(2)for checking of resources in resource usage graph I don’t see any unit . It gives zero in total and commulative although activity had been started. or it gives after finishing of activity.
If any body know the solution please reply.
Minhas
In P3e I have assigned resources on given activities. Resource units are labour and material. Most of atvities are linked togather. But One activity creates a huge lag. if I remove resouce from that activity then automatically lag removes. I don’t know where from that lag comes. I need to assign resource on that activity.That activity repeats many times in my schedule.
(2)for checking of resources in resource usage graph I don’t see any unit . It gives zero in total and commulative although activity had been started. or it gives after finishing of activity.
If any body know the solution please reply.
Minhas
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?