Skip to content

Physical % And Duration %

Suresh Sankarankutty PMPMember for 20 years 2 months
Created
6
1
0
I think this subject might been discussed earlier but i couldnt get the exact answer to clear my doubt.

Eg: Senario: Project Early start date is : 01.01.2007
Early finish date : 10.01.2007
Total Duration 10 Days
Data date is 05.01.2007

Now, in this senario, the duration % complete would be 50% on 5th Jan. But in reality the physical % completed (the real work done in the plant) would be 30 %. Now , i want to make comparison chart to show what duration is sofar completed and what physical progress we have acheived. In p3e i seen each day when you update the schedule with aplly actuals the project will show the duration % complete automatically. Now if you put the column of physical % complete that will be the same of the duraiton % complete. I really get confuse on those stuff. What i want to know is . The reality work completed would be entered in to a column manually and how can i see the total % of that. I can enter the real work % in to a user created column for each activity but i have to get the total % of that all i entered. Please let me clear my doubt. I would prefer to have discussion from simple theory.

Thank you
Suresh


6 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Suresh,

    % complete in P3e is worth a study.
    In a recent thread "Level of Effort" it was discussed: http://planningplanet.com/forum/forum_post.asp?fid=1&Cat=8&Top=35365.
    The best way to get informed on the meaning of attributes is to switch on the "hint help" e.g. under view. then e.g.: Move mouse into the table area --> right button --> "Columns" --> expand % complete --> (right)click onto the item you want to know --> a window appears with a good explanation.

    Hope this will help

    Dieter
  2. 0
    Suresh Sankarankutty PMP ·
    Dieter, thank you very much. Let me study through.
  3. 0
    Khuong Do ·
    Dear Suresh!
    Actvity have 3 percent complete type : duration, units, physical.
    Depend on which type you choose for activity, the value will reflect in "Activity % complete" column.
    The main factor you should focus when analyse updated schedule is "Activity % complete" column, not physical % or duration %.
    Duration, unit, physical % column is just used for temporary store.
    Calculation of Earned value will base on activity % complete.
    So, there will be no confict if your duration and physical % are diferent. Because Primavera just look at Activity % complete for calculation.

    Please feel free to contact me if you have problem

    Thanks
    Khuong
  4. 0
    Suresh Sankarankutty PMP ·
    Dear Khuong
    You are exactly right. But its simple question.
    How can get the % completed on basis of the user_entered column for actual completion.

    Eg: everyday i will put the progress % in a userdefined column. I want the total % for that in the top of the WBS. So that i can forcaste, howlong our duration is completed and howmuch % we completed so far in reality.

    Activity % complete will only give you % on basis of the duration and it could be different from the reality. Isnt it ?

    Thank you
  5. 0
    Khuong Do ·
    Hi Suresh

    We can not get activity % complete from UDF through Global change fuction.

    I suggest that you should update progress directly to physical % complete field, instead of UDF.

    But’Physical % complete’ is not rolled up, because it is a
    discrete, user entered value assigned to an activity. Since
    ’Physical % Complete’ does not relate to the duration,
    units or costs of the activity, there is no common
    denominator to use for the summary.

    However there is a workaround to roll-up physical % complete to WBS level.
    Workaround:
    It is possible to configure the Activity’s ’Performance %
    complete’ to equal the ’Physical % complete’.
    Performance % complete can be rolled up to the summary
    bands. However, to achieve this, the following three
    statements need to be true:
    1) The ’% Complete type’ of the activities must be
    set to ’Physical % complete’. This option is located
    in the General tab in the Activities View (Note: this
    will set the ’Activity % complete’ value to be equal
    to ’Physical % complete’. This will also impact the
    Earned Value calculation.)
    2) The ’Technique for calculating performance %
    Complete’ needs to be set to Activity % complete.
    This option is located in the Earned Value tab in the
    WBS View (Note: this will set the ’Performance %
    complete’ value to be equal to Activity % complete,
    which equals Physical % complete).
    3) Finally, in order for the Performance %
    Complete to be rolled up to the summary band(s),
    costs need to be assigned to the activity. These
    costs must also be present in the Primary baseline.
    Please Note:
    At the summary level, the Performance %
    complete is calculated as follows:
    Performance % Complete = (BCWP * 100) / BAC
    (Where the BCWP is the Budgeted Cost of
    Work Performed and the BAC is the Budget At
    Completion)
    BCWP is calculated as Activity % Complete *
    Baseline Total Cost
    By setting the 3 conditions above, the Activity %
    complete will equal the Physical % complete thus
    ensuring that the summary value for Performance %
    complete is calculated with regard to the Physical %
    complete, weighted by the activities’ cost.

    Thanks & regard
    Khuong
  6. 0
    Dieter Wambach ·
    Suresh

    I absolutely agree with Khuong. In addition I stumbled over a sentence of yours: "So that i can forcaste, howlong our duration is completed and howmuch % we completed so far in reality."
    So I have the impression, you want to forecast something. From where do you get %-complete? In the past I had to learn that an estimation of %-complete is absolutely unreliable, but if the people estimate which date they’ll finish their work, it will be much more reliable.
    Would it be an alternative, to use the expected finish date?

    Maybe I understood you wrong.

    Regards

    Dieter

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?